Etihad Railway Project Stage 2, Package 2D (C0308) Execution of Temporary Traffic Management Works at Junction Z5 -Sharjah
This project was part of the Etihad Railway Project Stage 2, Package 2D (C0308), focusing on the execution of temporary traffic management works at Junction Z5 in Sharjah. The scope included earthwork, cutting, filling, road work, and rail track preparation to facilitate safe and efficient traffic management during the railway construction phase. Conducted under project reference C0308-CRCNPC-RGCC-CL-00108, the project was executed by RGCC in collaboration with the CRCC-NPC JV and under the direction of Etihad Rail. The project was successfully completed, with a total value of AED 3,185,017.68.
End
2022-11-15
Scope of Work
Earthwork, Cutting, Filling, Road Work, Rail Track
Start
2021-08-26
Value
3,185,017.68 AED
Client
Etihad Rail PJSC