Helio Abu Al Abiyad (Zayed Link and Tal Moreeb Expansion)
This project involved essential earthwork activities, including cutting, filling, and site levelling, as part of the Helio Abu Al Abiyad development, which encompasses the Zayed Link and Tal Moreeb expansion. Undertaken under project reference 0026-NBHH-RAMA-09-GABY-SS, the project was executed by RGCC in collaboration with Nael & Bin Harmal, under the direction of ALDAR. With a total project value of AED 6,000,000.00, the works were completed efficiently and to a high standard, supporting the development and expansion of key infrastructure in Abu Dhabi.
End
2021-09-17
Scope of Work
Earthwork, Cutting, Filling
Start
2021-07-30
Value
6,000,000.00 AED
Client
ALDAR PJSC