Levelling and Backfilling works for estates affected by the removal of Ghashaba Square and Move to Jubaib Area

This project involved levelling and backfilling works for estates impacted by the removal of Ghashaba Square, facilitating their relocation to the Jubaib area in Al Ain. The works included precise grading and road preparation to ensure a stable and uniform ground base suitable for residential and infrastructural development. The project was executed under project reference DMTC-RGCC-WCC02-081221, with RGCC as the contractor and DMTC as the consultant, under the authority of the Al Ain Municipality. The project was successfully completed with a total value of AED 14,788,000.00.

End

2021-10-16

Scope of Work

Earthworks & Road work

Start

2020-05-16

Value

14,788,000.00 AED

Client

Department of Municipalites & Transport - Al Ain City Municpality